This will be a short post, just to keep everyone updated. Work continues toward completion.
Drywall has been completed, followed by sanding, priming of ceilings and walls, and finishing of ceilings. All done by BERGERON RENOVATIONS REMODELING, & DRYWALL CONTRACTORS
Repurposed Maple Flooring reclaimed last Spring and stored has been installed in the Main Space
;
Install, preparation and priming of trim has begun. Door package to be delivered next week!
.
Tile Floors in Bathroom and Shower are completed. Shower Walls coming up next!
ERV Ductwork is Installed, ready for Transportation to Holyoke!
What is up Next?
Completion of Flooring in the Barnacle.
Completion of Tile Work in Bathroom
Finish Electrical.
Trim package completed and Finished.
Cabinetry installed. Countertops Installed. Tile Backsplash installed.
Fixtures in Bath installed.
Hardware installed.
Walls finish coated.
We’ll keep you Posted